Punta Cana Project
Concerning the Punta Cana project, here is the preliminary time-line and cost estimate for the construction projects coming up:
- Finalized plans for parsonage and multipurpose building-December 15,2007
- Begin footings for parsonage and multipurpose building- January 2008
- Pay remaining debt of $27,000 on property- Feb. 28, 2008
- Work primarily on parsonage- Feb- June 2008
- Finish parsonage and begin main work on multi-purpose building- July 2008
- Multi-purpose building construction- July-October
- Begin worship center construction- November 2008
- Worship center construction- November 2008- April 2009
- Dedication of worship center- May 2009
See Floor Plans
Cost estimates here run from $12,000-16,000 pesos per square meter, as construction is measured here.
The resulting estimate, based on an average of $14,000 pesos per square meter is as follows:
| Parsonage |
180 square meters of construction $2,520,000 pesos or $76,363 dollars |
| Multi- purpose building |
504 square meters(168 per floor) $ 7,056,000 pesos or $213,818 dollars |
| Worship center |
600 square meters(1 floor, with balcony) $8,400,000 pesos or $254,545 dollars |
| Total preliminary estimated cost: $544,726 dollars |
We need the following:
- Churches that will help underwrite the cost of this project
- U.S. church short term work teams to come for a week of work on the project. October 2008 is still open and several dates in 2009, so e-mail at ryork@codetel.net.do or call at 809/550-9695(home) or 809/458-6840(mobile) if you’re interested in helping.
|